Mandatory vs Discretionary Project Management Dependencies (2024)

Category: Project Management Professional (PMP)® Exam using A Guide to the Project Management Body of Knowledge (PMBOK® Guide)

Mandatory vs Discretionary Project Management Dependencies (1)Project management dependencies determine the order in which various activities should be completed. These dependencies usually documented as an activity attribute and help in sequencing the activities on the project schedule network diagram. As you prepare for your Project Management Professional (PMP)® exam, it is important to know the difference between discretionary dependencies and mandatory project management dependencies.A mandatory dependency is one that “must be” carried out at a particular time.

It is usually requirement of some kind based on contracts, laws, company procedures, physical limitations, etc. When the sequence of events is developed for various aspects of the process, mandatory dependencies are placed where they must happen.A discretionary dependency is one that isn't based on a "have to", but on a "should". These decisions are usually based upon best practices, business knowledge, etc. They are placed on the project diagram where the team members would like them to occur.

Since discretionary project management dependencies are more arbitrary, they should be fully documented so the reasons for their placement can be maintained and available during future revisions. As a project progresses and adjustments are needed, discretionary dependencies are often reviewed for possible alterations.

For more PMP® exam tips, watch this video:

Build a PMP® Exam Study Plan

Mandatory vs Discretionary Project Management Dependencies (2024)

FAQs

Mandatory vs Discretionary Project Management Dependencies? ›

Conclusion. In short, mandatory dependencies are inherent in the nature of the work and cannot be changed. In contrast, discretionary dependencies are based on the preferences or best practices of the project team and can be changed if necessary.

Who or what determines which dependencies are mandatory? ›

The project management team determines which dependencies are internal during the process of sequencing the activities. Why isn't it both? "Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work."

What are the 3 types of dependencies in project management? ›

Here are the most common types of task dependencies:
  • Finish to Start (FtS): This is the most common task dependency. ...
  • Finish to Finish (FtF): Task B cannot finish until Task A is also completed. ...
  • Start to Start (StS): Task B cannot start before Task A starts.

Are mandatory dependencies sometimes referred to as hard logic or hard dependencies? ›

Hard logic dependencies are also known as mandatory dependencies. These dependencies are usually legally or contractually required. They can also be directed by company procedures or physical limitations.

What is mandatory dependency in project management? ›

What is a mandatory dependency? In project management, a mandatory dependency is one that's a non-negotiable requirement. Sometimes referred to as hard logic, this type of dependency means that the next task can't be started until the previous one has been completed.

What is the difference between a mandatory dependency and a discretionary dependency? ›

Mandatory dependencies are inflexible and must be followed, while discretionary dependencies are more flexible and can be adjusted as needed.

What is an example of a discretionary dependency in project management? ›

An example of a discretionary dependency is if you have two tasks that need to be completed, but the order in which they are completed does not matter. I.E., we will paint the house's siding before we paint the trim of the home.

What is an example of a mandatory dependency? ›

A common example of a mandatory dependency is when building a house. The foundation must be laid before the walls can be built, and the walls must be built before the roof can be installed.

What are discretionary dependencies defined by the project team? ›

A discretionary dependency is one that isn't based on a "have to", but on a "should". These decisions are usually based upon best practices, business knowledge, etc. They are placed on the project diagram where the team members would like them to occur.

What are the 4 types of dependencies in project management? ›

4 standard dependency types in project management
  • Finish-to-start dependency. In a finish-to-start dependency, one element requires the completion of another before you can begin it. ...
  • Finish-to-finish dependency. ...
  • Start-to-start dependency. ...
  • Start-to-finish dependencies.
Mar 10, 2023

What is the difference between discretionary dependency and mandatory dependency in project planning and scheduling? ›

Determination of mandatory dependencies in the process of sequence activities is undertaken by the project management team. The program's limitations in the scheduling tool should not be mistaken with mandatory dependencies. Discretionary dependencies may be known as preferred logic, preferential logic, or soft logic.

What are mandatory dependencies sometimes called? ›

Mandatory dependencies are sometimes called soft logic or preferred logic. They can and will change during a project lifecycle and/or as your PMO and project teams develop a deeper understanding of the projects you work on and get better data.

What are discretionary dependencies or soft logic? ›

Discretionary dependencies, also known as preferential or soft logic, are a type of dependency in project management. They are used to indicate that one task is preferred to be completed before another, but it is not absolutely necessary.

What is a discretionary project? ›

A discretionary project is one that requires the exercise of judgement or deliberation by a public agency in determining whether the project will be approved, or if a permit will be issued.

What is a mandatory internal dependency? ›

A mandatory internal dependency is often a physical or legal constraint to the start of project activity. A discretionary internal dependency is a choice by the project team according to factors such as cost, the availability of employees, or best project management practice.

Which dependency is the least common in project management? ›

Types of dependencies

The most common dependency relationship is a finish-to-start relationship. Task P (predecessor) must be finished before task S (successor) can start. The least common relationship is the start-to-finish relationship.

Who is responsible for dependency management? ›

Typically, the Project Manager is responsible for dependency management. If the organisation has a PMO, the services of the PMO can be enlisted to facilitate and manage external dependencies whilst the Project Manager manages internal dependencies.

Who identifies dependencies in Agile? ›

Ensuring everyone in the team knows the dependencies and how they affect the project helps. By being open and honest with one another, team members can identify dependencies early on, prioritize them, plan for them, decrease risks, collaborate with stakeholders, communicate across teams, and find solutions to issues.

What is a mandatory dependency? ›

A mandatory dependency is one that “must be” carried out at a particular time. It is usually requirement of some kind based on contracts, laws, company procedures, physical limitations, etc.

What is dependency determination? ›

Definition of Dependency Determination. A technique used to identify the type of dependency that is used to create the logical relationships between predecessor and successor activities.

Top Articles
Latest Posts
Article information

Author: Aracelis Kilback

Last Updated:

Views: 5747

Rating: 4.3 / 5 (44 voted)

Reviews: 83% of readers found this page helpful

Author information

Name: Aracelis Kilback

Birthday: 1994-11-22

Address: Apt. 895 30151 Green Plain, Lake Mariela, RI 98141

Phone: +5992291857476

Job: Legal Officer

Hobby: LARPing, role-playing games, Slacklining, Reading, Inline skating, Brazilian jiu-jitsu, Dance

Introduction: My name is Aracelis Kilback, I am a nice, gentle, agreeable, joyous, attractive, combative, gifted person who loves writing and wants to share my knowledge and understanding with you.